محطة مياه العريش( المساعيد 2 ) شمال سيناء
Civil Defense, Fire Alarm & Firefighting Systems Works – Seawater Desalination Plant, Masaeed 2, Arish City
Scope of Work Summary:
- Supply & installation of firefighting pump set complying with NFPA 20, consisting of:
- Main electric fire pump: 250 GPM
- Diesel backup fire pump: 250 GPM
- Jockey pump: 12.5 GPM
- Supply & installation of seamless black steel piping (Schedule 40) ranging from 4" to 1" diameter.
- Supply & installation of fire hose cabinets, complete with 1” and 2.5” fire hoses.
- Supply & installation of various types of fire extinguishers:
- Dry powder
- CO₂
- Foam (capacities 9L & 45L)
- Supply, installation, testing & commissioning of total flooding CO₂ fire suppression systems.














































Preventive And Curative Maintenance
1-Total Image and Lights
2-Electric Boards & Earthling systems
3-Air Compressors
4-Fire Fighting/Alarm Equipment & lines
5-Hydraulic and Electric Lifts
6-Painting
7-Shops including Air conditions & Refrigerators
8-Oil suction pumps & oil & grease pumps



















Preventive Maintenance
1- Preventive Maintenance Ring Main Unit (RMU).
2- Transformers Test.
3- Main Distribution Panel Preventive maintenance.
4- Power Factor Panel Preventive maintenance.

























مشروع سدود المملكة العربية السعودية
Supply and install 5 m poles for fixing IP camera and level switch for monitoring Systems at KSA Dams project with Giza Arabia as contractor and Saudi Arabia Government as an owner .











مشروع خالدة ابو الغراديق
For Playground : Renovation and Repairing for steel structure and civil work including concrete repairing and piping enhancements including supply , welding ,fabrication new poles and pipes to enhance the steel structure. For AG Gas plant control room : Supply and install and construct for renovation Control Room building including supply new lighting fixtures , new FACP for Fire alarm system and new electrical MDB with all suitable connections















مشروع بدر الدين
Turn key job for Supply and construction for Villa El Obayied field Accommodation building including Electrical, Mechanical,Plumbing,Civil work,HVAC , Fire alarm system












Exxon Mobil مشروع لوحات
Supply and install new cast resin busway for old grease plant and new grease plant including supply and install new LVSWG and construction new electrical Room with all a required civil and electrical works .











مشروع ابو رديس
Install CO2 fire suppression fighting system for 20 Substation at Petrobel Co. including Fire fighting pipes and Cylinders cabinets , Electrical,mechanical, Civil works










مشروع بترول اسيوط
Install FM200 Fire fighting system for 9 Labs at ASORC Co. including Emt Conduits,laying Fire alarm cables , Addressable FACP